10. AWARD CONTRACTS FOR THE CONSTRUCTION OF THE ANNUAL ROADWAY
RESURFACING PROJECT (CIP #1352) AND THE CITYWIDE STORM DRAIN IMPROVEMENT
PROJECT (CIP #1358)
RECOMMENDED ACTION: That the City Council:
1) Approve award of a contract to Onyx Paving Company, Incorporated for construction of the Annual
Roadway Resurfacing Project (CIP #1352), and authorize the City Manager to sign the contract
and authority to approve change orders if necessary; and
2) Approve award of a contract to Onyx Paving Company, Incorporated for construction of the
Citywide Storm Drain Improvement Project (CIP #1358), bid in conjunction with this work effort,
and authorize the City Manager to sign the contract and authority to approve change orders if
necessary; and
3) Authorize the City Manager to sign a Standard Consultant Services Agreement with GMU
Geotechnical for materials observation and testing services for the Annual Roadway Resurfacing
Project (CIP #1352), as outlined in the Fiscal Impact Section; and
4) Authorize the City Manager to sign a Standard Consultant Services Agreement with GMU
Geotechnical for materials observation and testing services for the Citywide Storm Drain
Improvement Project (CIP #1358), as outlined in the Fiscal Impact Section; and
5) Authorize the City Manager to sign a Standard Consultant Services Agreement with WestLAND
Group, Incorporated, for surveying, construction staking and monument preservation for the
Annual Roadway Resurfacing Project (CIP #1352), as outlined in the Fiscal Impact Section; and
6) Authorize the City Manager to sign a Standard Consultant Services Agreement with WestLAND
Group, Incorporated, for surveying, construction staking and monument preservation for the
Citywide Storm Drain Improvement Project (CIP #1358), as outlined in the Fiscal Impact Section;
and
7) Authorize the City Manager to sign a Standard Consultant Services Agreement with GHD, Inc. for
professional engineering services support during construction for the Citywide Storm Drain
Improvement Project (CIP #1358) and the associated expenditure as noted in the Fiscal Impact
Section.
8) Approve expenditure and budget adjustments outlined in the Fiscal Impact Section for FY24
Roadway Resurfacing Project.