NOTICE OF COMPLETION: ALLEY REHABILITATION PROJECT (AREA A - PHASE
II) – F2M25-27, C2M25-19, M2M25-141
On April 28, 2025, the City Council awarded a contract to Kalban Inc. for the Alley
Rehabilitation Project (Area A / Phase II) in the amount of $976,785.00. One negative
change order was issued in the amount of $21,454.50. The change order addressed the
bid item quantity adjustment due to over-estimation by the design engineer. This resulted
in a reduction to the original contract and a final contract cost of $955,330.50. This project
has been inspected by staff and all work has been completed in accordance with the City’s
requirements and specifications. As such, it would be appropriate for the City Council to
accept this project as complete and instruct that the Notice of Completion be filed with the
County of Los Angeles Recorder’s Office.
Recommended Action:
City Council accept the work of Kalban Inc. for the Alley
Rehabilitation Project (Area A / Phase II) (C2M25-19) as complete in the amount of
$955,330.50; direct the City Clerk to file a Notice of Completion with the County of Los
Angeles for recordation; instruct the Finance Director to release the 5% retention 35 days
from the date of recordation if no liens are filed; and, direct staff to undertake the steps
necessary to finalize Council’s action. (M2M25-141)
8