A. Award Bid SP2060-CT to Shimmick Construction Company, Inc. and RFP SP2060-CM to Bureau
Veritas North America, Inc; Authorize the City Manager to Negotiate and Enter Into Contracts with
Shimmick Construction and Bureau Veritas and a Contract Modification with Dokken Engineering,
Inc.; Authorize the City Manager to Accept Grant Award from the Highway Bridge Program and All
Grant Renewals, and to Execute All Necessary Associated Documents for the Pier Bridge
Replacement Project
Recommended Action
Staff recommends that the City Council:
1. Adopt a finding that the project was previously analyzed in the certified Santa Monica
Pier Bridge Replacement Project Recirculated Final Environmental Impact
Report/Environmental Assessment in accordance with CEQA;
2. Adopt Addendum #1 to the Santa Monica Pier Bridge Replacement Project Recirculated
Final Environmental Impact Report/Environmental Assessment;
3. Award Bid #SP2060-CT to Shimmick Construction Company, Inc. for the Pier Bridge
Replacement Project for the Public Works Department;
4.
Authorize the City Manager to negotiate and execute a contract with Shimmick
Construction Company, Inc. in an amount not to exceed $35,579,292 (including a 20%
contingency), and, if necessary, authorize the City Manager to negotiate and execute a
bridge equipment lease agreement with Acrow Corporation of America for lease of a
temporary pedestrian bridge system;