39.
Treasurer and Tax Collector Warehouse Deferred Maintenance Repairs
Project Construction Contract
Recommendation: Approve and authorize the Director of Public Works to
finalize and execute a change order with PCN3, Inc., for an amount not to
exceed $1,180,000, to revise the proposed new fire sprinkler system to comply
with the fire code requirements for the intended warehouse operations and
functions (1). Approve and authorize the Director to finalize and execute a
change order with PCN3, Inc., for an amount not to exceed $1,180,000, to
incorporate full-height, fire-rated interior partition walls in the warehouse to
comply with the fire code requirements for the intended warehouse operations
and functions. The two proposed change orders are for a total amount not to
exceed $2,360,000. Sufficient funding is available in the approved project
budget to cover the costs of the proposed change orders. Find that the scope of
work to be carried out under the proposed change orders is within the scope of
the previous findings of exemption under the California Environmental Quality
Act. (Department of Public Works) APPROVE 4-VOTES (25-5091)