B.10. AMENDMENT TO INCREASE PROJECT CONTINGENCY FOR THE
8305 SANTA MONICA BOULEVARD BUILD-OUT PROJECT [H.
COLLINS, P. TICUN, E. HAMANT]:
SUBJECT: The City Council will consider approving Amendment No. 1 to
the Construction Agreement with PCL Construction Services, Inc. to
increase the project contingency amount from 20% to 25% for the 8305
Santa Monica Boulevard Build-Out Project.
RECOMMENDATIONS:
1) Approve Amendment No. 1 to the
Construction Agreement with PCL Construction Services, Inc. to increase
the project contingency amount for the 8305 Santa Monica Boulevard
Build-Out Project from 20%, which is $346,468, to 25% by authorizing an
additional $86,618 for an updated total project contingency amount not to
exceed $433,086 and a new total contract amount not-to-exceed
$2,165,430; 2) Authorize the Facilities and Field Services Division
Manager to approve Change Orders to the Agreement; 3) Authorize the
City Manager, or designee, to execute all documents incident to the
Agreement; and 4) Authorize the Director of Finance & Technology
Services to transfer $86,618 in budget from savings in CIP 57-02
Holloway Motel to CIP 40-03 8301 Santa Monica Boulevard.