Whittier
City Council
8.I.
Summit Dr. Water Main Replacement Project – Award of Contract
Recommendation:
1) Adopt Resolution No. WUA-2025-04 amending the Fiscal Year 2025-2026
Budget in the amount of $809,750 for the Summit Dr. Water Main
Replacement Project.
2) Award the construction contract to Williams Pipeline Contractors, Inc., in
the amount of $735,750 for the construction of Summit Dr. Water Main
Replacement Project;
3) Reject all other bids;
4) Authorize the Executive Director to sign the construction contract on behalf
of the Whittier Utility Authority; and
5) Approve $74,000 in contingency funding for the Summit Dr. Water Main
Replacement Project subject to the approval of the Executive Director.