10.11 Consideration of Award of a Construction Contract for the
HSIP Cycle 11 Intersection Improvements at Florence
Avenue/Garfield Avenue and Eastern Avenue/Gage Avenue
(CIP No. 3936)
RECOMMENDATION: It is staff’s recommendation that the City
Council:
1. Accept FS Contractors, Inc.’s request to withdraw its bid for
the HSIP Cycle 11 Intersection Improvements at Florence
Avenue/Garfield Avenue and Eastern Avenue/Gage Avenue
(CIP No. 3936) and waive the forfeiture of FS Contractors, Inc.’s
bid guarantee;
2. Award a construction contract to Palp. Inc. dba Excel Paving.
in the amount of $437,073.00 for the HSIP Cycle 11
Intersection Improvements at Florence Avenue/Garfield
Avenue and Eastern Avenue/Gage Avenue (CIP No. 3936);
3. Authorize the City Manager to execute the Construction
Contract and approve change orders that may be necessary
during construction to cover any unforeseen condition in an
amount not to exceed 10% of the construction contract; and
4. Appropriate an additional $110,470 in Measure M funds to
cover all construction and project management costs,
including contingency.
CONCLUSION: If the Construction Contract is awarded, staff will
process the contract for signatures and coordinate a pre-construction
meeting.
FISCAL IMPACT: The total estimated construction cost is $437,073.
The total cost for the construction phase, including construction,
contingency (10%) and construction management and inspection is
$527,970.
The City’s FY25/26 capital improvement budget includes a total
budget of $417,500 for the construction of the Project, which includes
$375,750 in HSIP Funds and $41,750 in general funds, as a local
match. Therefore, an additional appropriation of $110,470 in Measure
M funds is recommended to cover the shortfall.
ATTACHMENTS:
Exhibit 1 - Contract Services Agreement