D. Accept Completed Improvements and Authorize the Filing of a Notice of
Completion for the Public Safety Center Upgrades Project No. 31028 On
October 22, 2024, the City Council awarded a construction contract to
Royal Construction Corp. for the Public Safety Center Upgrades Project.
The total construction budget, including a 10% contingency, was
$2,626,800.00. On June 10, 2025, the City Council adopted Resolution No.
2025-30 amending the City’s Fiscal Year 2024-25 CIP budget to
appropriate additional funds in the amount of $255,850.00 to cover the
costs of unforeseen conditions. All construction improvements have been
completed and have been accepted by City staff. A notice of completion
will be filed with the Los Angeles County Recorder upon approval by the
City Council. The release of retention funds will occur 35 days after the
filing of the notice of completion.
Recommendation: That the City Council take the following actions:
1. Accept the completed improvements for the Public Safety Center
Upgrades Project No. 31028 as performed by Royal Construction,
Corp.; and
2. Authorize the recordation of Notice of Completion with the Los
Angeles County Recorder and the release of retention funds 35 days
thereafter.
Staff Report