10. APPROVAL OF A CHANGE ORDER TO CONTRACT WITH PRECISION
ENVIRONMENTAL FOR ADDITIONAL ABATEMENT AT THE ALHAMBRA
COMMUNITY CENTER - F2M22-65, C2M25-45, M2M26-14
On October 13, 2025, the City Council awarded a contract to Precision Environmental for
building demolition services for the Alhambra Community Center in an amount not to
exceed $424,000.00. The project was originally proposed to provide demolition services,
but during the demolition process, staff and the contractor identified additional asbestos
material in the crawl space and within the building walls that was no previously detected.
The additional work includes the disposal of all asbestos material and ensuring that the
decontaminated building is prepared for demolition.
Recommended Action: City Council approve Change Order No. 1 for the contract
with Precision Environmental for demolition services for the Alhambra Community Center
(Contract No. C2M25-45), increasing the contract amount by $308,393.06 and bringing
the total revised contract value to an amount not to exceed $732,393.06; appropriate funds
in Alhambra Community Center account number 310.60.6010.92338 in the amount of
$308,393.06 to complete the project; and, direct staff to undertake the steps necessary to
finalize Council’s action. (M2M26-14)