Item 55: Pure Water Phase 1 Consolidated Action - Contractor Contract Time Extensions.
Total Estimated Cost of Proposed Action and Funding Source:
These actions have no cost impacts as they are requesting authority for time extension
only.
Council District(s) Affected: Citywide.
Proposed Actions:
Adopt the following Ordinances which were introduced on 2/10/2026, Item 51 Subitems
A-C, (Council voted 6-0, Councilmember Campbell-not present, Councilmember
Whitburn-not present, Councilmember Campillo-not present):
Subitem-A: (O-2026-84)
Ordinance authorizing the Mayor, or designee, to extend the obligations of Construction
Contract K-21-1848-DBB-3 with OHLA USA, Inc. for an additional twelve months in
connection with the Pure Water Phase 1 Morena Conveyance North Project.
Subitem-A: 6 votes required pursuant to Charter Section 99.
Subitem-B: (O-2026-80)
Ordinance authorizing the Mayor, or designee, to extend the obligations of Construction
Contract K-21-1744-DBB-3-A with W.A. Rasic Construction, Inc. for an additional thirty-
two months in connection with the Pure Water Phase 1 North City Pure Water Pipeline
and Subaqueous Pipeline Project.
Subitem-B: 6 votes required pursuant to Charter Section 99.
Subitem-C: (O-2026-79)
Ordinance authorizing the Mayor, or designee, to extend the obligations of Construction
Contract K-21-1867-DBB-3 with PCL Construction, Inc. for an additional twenty-nine
months in connection with the Pure Water Phase 1 Metropolitan Biosolids Center
Improvements Project.
Subitem-C: 6 votes required pursuant to Charter Section 99.
Committee Actions Taken:
This item was heard at the Environment Committee meeting on January 22, 2026.
ACTION: Motion by Committee Member LaCava, second by Vice Chair Campbell, to
recommend Council approval of staff’s proposed actions.
VOTE: 3-0; Elo-Rivera-yea, Campbell-yea, LaCava-yea.
Engineering & Capital Projects: Elif Cetin, (619) 533-3794
City Attorney Contact: Elizabeth Cason