Santa Ana
City Council
18.
Award a Construction Contract to R.J. Noble Company for the Construction of the
Grand Avenue Rehabilitation from Edinger Avenue to McFadden Avenue Project
(Project No. 23-6700) (Non-General Fund)
Department(s): Public Works Agency
Recommended Action: 1. Approve the Project Cost Analysis for a total estimated
construction delivery cost of $1,243,213, which includes $994,570 for the
construction contract, $149,186 for contract administration, inspection, and
testing, and a $99,457 for unanticipated or unforeseen work.
2. Award a construction contract to R.J. Noble Company, the lowest responsible
bidder, in accordance with the base bid in the amount of $994,570, subject to
change orders, for construction of the Grand Avenue Rehabilitation from Edinger
Avenue to McFadden Avenue Project (No. 23-6700), for a term beginning March
3, 2026, and authorize the City Manager to execute the contract.
3. Determine that, pursuant to the California Environmental Quality Act, the
recommended actions are exempt from further review. Categorical Exemption
Environmental Review No. ER-2023-91 will be filed for Project No. 23-6700.