9I. ACCEPTANCE OF THE 8900 AND 8911 PACIFIC AVENUE DEMOLITION PROJECT
BY THE CITY COUNCIL OF THE CITY OF STANTON, CALIFORNIA
The 8900 and 8911 Pacific Avenue Demolition Project consisting of the demolition and
abatement of two vacant 4-plex buildings located at 8900 and 8911 Pacific Avenue is now
complete. The final construction cost for the project was $150,000, the contract award
amount. The City Engineer, in his judgment, certifies that the work was satisfactorily
completed as of February 19, 2026, and recommends that the City Council accept the
completed work performed on this project.
RECOMMENDED ACTION:
1. City Council find that the project is categorically exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301(l)(3), Class 1 - minor
alteration and demolition of existing small structures; and
2. Accept the completed improvements for the 8900 and 8911 Pacific Avenue Demolition
Project as certified by the City Engineer, and establish February 19, 2026, as the
official date of completion; and
3. Approve the final construction contract amount of $150,000.00 with Integrated
Demolition and Remediation, Inc.; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment) with the County Clerk-Recorder of the County of Orange;
and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to
Integrated Demolition and Remediation, Inc. in the amount of $7,500.00.