Agenda Item
· El Segundo
City Council — Item 16
Original agenda text
Item
16. Construction Change Order Presentation for the Urho Saari Swim
Stadium / Plunge Renovation Project
Recommendation -
1. Receive and file presentation.
2. Authorize an additional appropriation of $950,000 from the General Fund
Reserve to the Plunge Capital Improvement Project fund for the
remaining change orders and continuing the construction management
services to complete Urho Saari Swim Stadium / Plunge Renovation
Project.
3. Authorize staff to approve the remaining change orders, estimated to be
$1,350,000 above the already approved $2,000,000, for a change order
total of $3,350,000, to complete the project.
4. Alternatively, discuss and take other action related to this item.