Tustin
City Council
9. ACCEPTANCE OF PUBLIC IMPROVEMENT AND AUTHORIZATION TO
FILE THE NOTICE OF COMPLETION FOR THE CAMINO REAL PARK
PLAYGROUND RENOVATION The Camino Real Park Phase 1
Playground Renovation has been completed, and is now ready for City
Council acceptance. Phase 2 of the project, the Picnic Shelter
Renovation, has been budgeted but is not yet complete and is not
included in this Notice of Completion.
Recommendation: Recommend the City Council: 1. Adopt Resolution No.
26-21 accepting the Camino Real Park Phase 1 Playground Renovation,
and 2. Authorize the City Clerk to file the Notice of Completion with the
County Recorder's office for Phase 1 only. RESOLUTION NO. 26-21 A
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, ACCEPTING THE WORKS OF IMPROVEMENT AND
AUTHORIZING THE RECORDATION OF THE NOTICE OF
COMPLETION FOR THE CAMINO REAL PARK PLAYGROUND (CIP NO.
20096) Fiscal Impact: On November 4, 2025, the City Council authorized
an appropriation in the FY 2025/2026 Capital Improvement Program from
the Park Development Fund in the amount of $ 1,000,000 for the Camino
Real Playground and Picnic Shelter Renovation project (CIP No. 20096)
which consists of two separate phases under distinct contracts. Project
allocations included: • Phase 1 Playground - Innovative
Playgrounds.........................$486,979.04 • Phase 2 Picnic Shelter - Icon
Shelter Systems .........................$421,864.76 • Total Contract
Expenditures..............................................$908,843.80 The final cost of
the playground renovation contract was $486,979.04, with no change
orders under the original scope of work. Phase 2 (Picnic Shelter
Renovation) is currently in progress and will be presented to City Council
for acceptance at a later date.