Walnut
City Council
8. Approve Change Order No. 1 for the Flood Plain Trail Erosion Repair Project
and Increase Construction Contingency Authority
contract for the Flood Plain Trail Erosion Repair Project in the amount of
$26,267.00;
2. Increase the total authorized construction contract amount from $93,095.00 to
$119,362.00;
3. Authorize staff to approve change orders not to exceed 20% of the revised
contract amount ($23,872.40); and
4. Authorize staff to approve and process payments to Hardy & Harper Inc. for
construction services.