Agenda Item
· Stanton
City Council — Item F
Original agenda text
Order of Business 9
9F. ACCEPTANCE OF THE CITYWIDE STREET SIGN REPLACEMENT PROJECT
(PHASE 2) (TASK CODE NO. 2022-102) BY THE CITY COUNCIL OF THE CITY OF
STANTON, CALIFORNIA
The Citywide Street Sign Replacement Project (Phase 2) which consisted of replacing
approximately 575 residential street name signs has been completed. The final
construction cost was $177,000.00, $3,090.00 above the contract award amount of
$173,910.00 due to two contract change orders utilizing the project contingency. The City
Engineer, in his judgment, certifies that the work was satisfactorily completed as of April
30, 2026, and recommends that the City Council accept the completed work performed
on this project.
RECOMMENDED ACTION:
1. City Council find that this project is exempt from the California Environmental Quality
Act (“CEQA”), Class 2, Section 15302 as replacement of existing structures and
facilities; and
2. Accept the completed improvements for the Citywide Street Sign Replacement Project
(Phase 2) as certified by the City Engineer, and establish April 30, 2026, as the official
date of completion; and
3. Approve the final construction contract amount of $177,000.00 with Square Signs LLC
dba Front Signs; and
4. Direct the City Clerk within ten (10) days from the date of acceptance to file the Notice
of Completion (Attachment) with the County Clerk-Recorder of the County of Orange;
and
5. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to
Square Signs LLC dba Front Signs in the amount of $8,850.00.