Agenda Item
· Santa Clarita
City Council — Item 13
Original agenda text
Item
13. CONSULTANT PREPARATION OF THE ENVIRONMENTAL IMPACT
REPORT FOR THE SUNRIDGE DEVELOPMENT CONTRACT - Per the
California Environmental Quality Act, an Environmental Impact Report must be prepared
for the Sunridge Development. This is a request for the City Council to award a contract
for the preparation of that required document for the project.
RECOMMENDED ACTION:
City Council:
1. Award a contract to Michael Baker International, Inc., for the preparation of the
Sunridge Development project Environmental Impact Report (Master Case 24-266) in
the amount of $875,102, and authorize a contingency in the amount $370,771, for a
total contract amount not to exceed $1,245,873.
2. Authorize the City Manager or designee to execute all documents, subject to City
Attorney review.