Agenda Item
· San Marino
City Council — Item 5
Original agenda text
Item
5. APPROVAL OF 1) CONTRACT AMENDMENT NO. 5 TO THE
PROFESSIONAL SERVICES AGREEMENT WITH DUDEK FOR
ENGINEERING SERVICES DURING CONSTRUCTION FOR THE LIFT
STATION IMPROVEMENT PROJECT, EXTENDING THE TERM THROUGH
JUNE 30, 2026 AND INCREASING TOTAL COMPENSATION BY
$10,000, 2) CONTRACT AMENDMENT NO. 2 TO THE PROFESSIONAL
S E R V I C E S A G R E E M E N T W I T H Z & K C O N S U L T A N T S F O R
CONSTRUCTION MANAGEMENT & INSPECTION SERVICES FOR THE
LIFT STATION IMPROVEMENT PROJECT, EXTENDING THE TERM
THROUGH DECEMBER 31, 2026, 3) INCREASE THE AUTHORIZED
C O N S T R U C T I O N C O N T I N G E N C Y F O R T H E L I F T S T A T I O N
IMPROVEMENT PROJECT BY $127,600, BRINGING THE TOTAL
CONTINGENCY AMOUNT TO $227,600, 4) AUTHORIZE THE PARKS
AND PUBLIC WORKS DIRECTOR/CITY ENGINEER TO APPROVE
ASSOCIATED PROJECT CHANGE ORDERS WITHIN THE AUTHORIZED
CONTINGENCY AMOUNT, 5) AUTHORIZE THE CITY MANAGER TO
EXECUTE THE AMENDMENTS ON BEHALF OF THE CITY, AND 6)
APPROPRIATE AN ADDITIONAL $145,231.60 TO ACCOUNT #700-
44-4600-8022 (LIFT STATION IMPROVEMENTS) FROM THE SEWER
ENTERPRISE FUND
Recommendation: Staff recommends that the City Council 1) approve Amendment
No. 5 with Dudek for engineering services during construction for the Lift Station
Improvement Project, extending the term through December 31, 2026 and increasing
total compensation by $10,000, 2) approve Amendment No. 2 with Z&K Consultants
for construction management and inspection services for the Lift Station
Improvement Project, extending the term through December 31, 2026, 3) increase
the authorized construction contingency for the Lift Station Improvement Project by
$127,600, bringing the total contingency amount to $227,600, 4) authorize the Parks
and Public Works Director/City Engineer to approve associated project change orders
within the authorized contingency amount, 5) authorize the City Manager to execute
the amendments on behalf of the City, and 6) appropriate an additional $145,231.60
to account #700-44-4600-8022 (Lift Station Improvements) from the Sewer
Enterprise Fund. If the Council concurs, an appropriate motion would be:
“I move to 1) approve Amendment No. 5 with Dudek for engineering services during
construction for the Lift Station Improvement Project, extending the term through
December 31, 2026 and increasing total compensation by $10,000, 2) approve
Amendment No. 2 with Z&K Consultants for construction management and inspection
services for the Lift Station Improvement Project, extending the term through
December 31, 2026, and 3) increase the authorized construction contingency for the
Lift Station Improvement Project by $127,600, bringing the total contingency amount
to $227,600, 4) authorize the Parks and Public Works Director/City Engineer to
approve associated project change orders within the authorized contingency
amount, 5) authorize the City Manager to execute the amendments on behalf of the
City, and 6) appropriate and additional $145,231.60 to account #700-44-4600-8022
(Lift Station Improvements) from the Sewer Enterprise Fund.”