Los Angeles
LA County Board
44. Bassett Park Building and Exterior Improvements Capital Project
Recommendation: Approve the revised total project budget of $3,600,000, from
a previously adopted budget of $3,000,000, for the Bassett Park Building and
Exterior Improvements Project, Capital Project No. 87571 (Project). Approve an
appropriation adjustment to reflect an increase of $600,000 in appropriation to
the Project, fully offset by the Avocado Heights - Athens Tipping Fees available
in the Department of Parks and Recreation’s operating budget, to fully fund the
revised Project. Authorize the Director to deliver the Project through a
Board-approved Job Order Contract. Find that the revised Project is exempt
from the California Environmental Quality Act. (Supervisorial District 1)
(Department of Parks and Recreation) APPROVE (26-5882)