Oceanside
City Council
5. City Council: Staff recommends that the City Council authorize the City 26-1648
Engineer to approve Construction Change Order No. 3 with
Fordyce Construction, Inc. (“Fordyce”), in the amount of
$640,444 for a total contract amount not-to-exceed
$4,973,502, for additional construction services for the
Crown Heights Community Resource Center Building
(“Crown Heights Community Center”); and authorize the
City Engineer to approve change orders required to finalize
construction and complete the rental agreement and
modular unit removal with Pacific Mobile Structures, Inc.
(“Pacific Mobile”) as needed per the construction schedule,
in an additional amount not-to-exceed $17,609 to cover
outstanding costs totaling $20,561 that exceed the
remaining $2,952 available under the existing agreement.