Agenda Item
· Calabasas
City Council — Item 7
Original agenda text
Item
7. Public Hearing and Adoption of a Resolution Approving the Energy Savings
Performance Contract Amendment with Willdan Energy Solutions, Inc.,
Approving the Equipment Lease/Purchase Agreement Lease Purchase and
Escrow Agreements with Webster Public Finance Corporation, and Adoption
of a Resolution Amending the Fiscal Year 2026-27 Operating and Capital
Improvement Budget to Increase Appropriations for the Energy Efficiency
Infrastructure Project
Recommendation:
Staff recommends that the City Council:
1. Conduct a public hearing and adopt Resolution No. 2026-2043 (attachment
B) making appropriate findings for energy conservation improvements, and
making findings pursuant to Government Code Sections 4217.12 and
4217.13, and authorizing related actions; and
2. Find the project exempt from review under California Environmental Quality
Act (CEQA), pursuant to Sections 15301, 15302, and 15303 the CEQA
Guidelines and Public Resource Code Section 21080.35; and
3. Authorize the City Manager to negotiate and execute a contract amendment
with Willdan Energy Solutions, Inc. (WES) to implement energy conservation
improvements at the Civic Center, Community Center, Tennis and Swim
Center, and several park facilities for a new estimated total amount not to
exceed $9,309,959 over an estimated two-year term; and
4. Authorize the City Manager (and other Authorized Officers) to negotiate and
execute an Equipment Lease Purchase Agreement with Webster Public
Finance Corporation (a subsidiary of Santander Bank, N.A.) for the
equipment lease/purchasing agreement for a total principal amount not to
exceed $6,283,289 with a 4.89% fixed interest rate over a 20-year term, to
negotiate and execute an Escrow Agreement, to pay costs associated with
entering into the Financing Documents, and approve or take other actions as
needed to complete the financing; and
5. Adopt Resolution No. 2026-2044 (Attachment I) amending the Fiscal Year
2026-27 Operating and Capital Improvement Budget to increase
appropriations for the Energy Efficiency Infrastructure Project.
NEW BUSINESS