Agenda Item 12

12. Progress Payment #7 and Final Acceptance in the amount of $118,100.39 due to\nGRBCON, Inc of Balwin Park, CA for Sewer Main and Miscellaneous Storm Drain\nImprovement Project 2023 (Project # 23-04).\nRECOMMENDED MOTION: Staff recommends that the City Council approve this\nProgress Payment #7 and Final Acceptance for Sewer Main and Miscellaneous\nStorm Drain Improvement Project 2023 (Project # 23-04) to GRBCON, Inc of\nBaldwin Park, CA and release 5% retention amount 35 days after Final Approval.