Huntington Park

City Council

July 16, 2024 Item #7

Agenda Item 7

7. CONSIDERATION AND APPROVAL TO AWARD A CONSTRUCTION\nCONTRACT FOR CIP 2019-14 ATP CYCLE V PROJECT\nRECOMMENDED THAT CITY COUNCIL:\n1. Award the contract to Palp Inc. DBA Excel Paving for the construction of CIP 2019\n14 ATP Cycle V Project as the lowest responsive, responsible bidder for a not to\nexceed fee of $2,592,810; and\n2. Approve a 10% construction contingency in the amount of $259,281; and\n3. Appropriate $2,852,091 to Account No. 202-8080-431.76-20 (State of California\nDepartment of Transportation reimbursable expense); and\n4. Authorize the City Manager to execute the construction contract agreement and\nall change orders in good faith.