Huntington Beach

City Council

September 17, 2024 Item #17

Agenda Item 17

17. 24-336 Accept the lowest responsive and responsible bid and authorize\nexecution of a construction contract with US Builders and\nConsultants Inc. in the amount of $579,600 for the Storm Water Pump\nStation Roof and Facilities Improvements Project, CC-1739 and\nappropriation of funds\nRecommended Action:\nA) Accept the lowest responsive and responsible bid submitted by US Builders and\nConsultants Inc. in the amount of $579,600; and ,\nB) Authorize the Mayor and City Clerk to execute a construction contract in a form\napproved by the City Attorney; and ,\nC) Appropriate $356,864 from Planned Local Drainage Fund undesignated fund balance\nto Drainage Fund account 21188009.82500.