Whittier

City Council

September 24, 2024 Joint Consent Calendar #M

Agenda Item M

12.M. 23-012 Community Center Roof Replacement Project – Award of\nContract\nRecommendation:\n1) Adopt Resolution No. 2024-58, amending Fiscal Year 2024-25 Budget\nwith an appropriation for 23-012 Community Center Roof Replacement\nProject;\n2) Award the construction contract to Best Contracting Services Inc., in the\namount of $574,525 for the 23-012 Community Center Roof\nReplacement Project;\n3) Reject all other bids;\n4) Authorize the City Manager to sign the construction contract on behalf of\nthe City; and\n5) Approve $57,453 in contingency for the Project subject to the approval of\nthe City Manager.