Agenda Item
· Placentia
City Council — Item C
Original agenda text
Order of Business 1
1.c. Acceptance Of Construction Work and Notice of Completion
for the Old City Hall Office Renovation Project, City Project
No. 5106 Fiscal Impact: Expense: $465,000.00 Original
Construction Contract $ 99,902.30 Approved Change
Orders No. 1 - 6 $ 0.00 Balancing Change Order No. 7 $
62,400.00 Construction Inspection Services $627,302.30
Total Construction Cost Available Budget: $49,441.40 FY
22-23 CIP Project Budget $49,441.40 Measure U Fund
https://placentia.granicus.com/GeneratedAgendaViewer.php?view_id=4&event_id=413 5/13
2/3/23, 1:38 PM https://placentia.granicus.com/GeneratedAgendaViewer.php?view_id=4&event_id=413
(795106-6185)
Recommended Action: It is recommended that the City
Council:
1) Authorize the City Administrator to approve Balancing
Contract Change Order No. 7 with A2Z Construct Inc.,
in the amount of $0.00; and
2) Accept the work performed by A2Z Construct Inc., for
construction of the Old City Hall Office Renovation
Project, City Project No. 5106 for a grand total
amount of $564,902.30; and
3) Authorize the City Administrator to file a Notice of
Completion with the Orange County Clerk-Recorder’s
Office for the Project; and
4) Authorize the City Administrator to release retention
funds in accordance with the terms of the contract.
Staff Report
Balancing Contract Change Order
NOC A2Z Construction Inc.