Baldwin Park

City Council

8. Authorize Additional Work and Approve a Contract Change Order for Stance Construction Company to Install Sewer House Connections and Abandon Septic Tanks as Part of the Work for the Calino Avenue Improvements Project It is recommended that the City Council: Authorize the additional work and approve the proposal from Stance Construction Company in the amount of $92,950.00 to connect 12 homes to new sewer infrastructure including lateral connections, septic tank abandonments, clean-out and appurtenant work; and, Authorize the Director of Public Works to execute a contract change order for the additional work; and, Authorize the Director of Finance to appropriate $92,950.00 from Fund No. 275 and to make the necessary budget adjustments. STAFF REPORT