Agenda Item
· Los Alamitos
City Council — Item G
Original agenda text
Order of Business 11
G. Notice of Completion for the New Dutch Haven Neighborhood Street
Rehabilitation Project (CIP 22/23-02) (Development Services)
The City of Los Alamitos hired a roadway contractor for street
improvements related to grind and overlay and slurry seal in the New
Dutch Haven Neighborhood as part of the City’s ongoing pavement
management program.
Staff is recommending that City Council accept the work as completed,
direct filing of the Notice of Completion, and authorize retention release as
prescribed by the Public Contract Code.
Recommendation:
1. Accept as complete the construction by Hardy and Harper, Inc. for the
New Dutch Haven Neighborhood Street Rehabilitation Project (CIP No.
22/23-02); and,
2. Direct the City Clerk to record the Notice of Completion/Final Report
with the County Recorder’s Office; and,
3. Authorize Staff to release the 5% retention to the contractor, in the
amount of $13,636.60, thirty-five (35) days after recordation of the
Notice of Completion.