Agenda Item
· Stanton
City Council — Item E
Original agenda text
Order of Business 9
9E. ACCEPTANCE OF THE FAMILY RESOURCE CENTER RENOVATION PROJECT
(PHASE I) BY THE CITY COUNCIL OF THE CITY OF STANTON, CALIFORNIA
The Family Resource Center Renovation Project (Phase I) consisting of new exterior
and interior lighting, new air conditioning units, wall and monument signage, painting of
the interior, new flooring, construction of a concrete walkway, new blinds, window tint,
and ceiling tiles, new quartz countertop at the reception area, and re-laminating of
existing kitchen cabinet faces and doors is now complete. The final construction cost for
the project was $694,856.85. The City Engineer certifies that the work was completed
as of October 15, 2023 and recommends that the City Council accept the completed
work performed on this project.
October 24, 2023
RECOMMENDED ACTION:
1. City Council declare that this project is categorically exempt under the California
Environmental Quality Act, Class 1, and Section 15301(a) as repair, maintenance,
and minor alteration of an existing public facility; and
2. Approve the final construction contract amount of $694,856.85 with A2Z Construct,
Inc.; and
3. Direct the City Clerk within ten (10) days from the date of acceptance to file the
Notice of Completion (Attachment) with the County Clerk-Recorder of the County of
Orange; and
4. Direct City staff, after thirty-five (35) days has elapsed from the filing of the “Notice of
Completion” with the County Clerk-Recorder, to make the retention payment to A2Z
Construct, Inc. in the amount of $34,742.84.