3. Approve Change Orders for Stance Construction and the Authorize
Additional Work by San Gabriel Valley Water Company as Part of City
Project CIP No. 22-040 - Calino Avenue Improvements
It is recommended that the City Council:
1. Authorize and approve the additional work for the proposal from
Stance Construction Company in the amount of $40,703.78 to add
265 linear feet of 8â sewer line; and,
2. Authorize and approve payment for the change order from Stance
Construction Company in a not-to-exceed amount of $34,410.97 for
incurred costs on rental equipment and insurance during the project
suspension period; and,
3. Approve added work for the proposal in the form of a deposit in a
not-to-exceed amount of $65,000.00 from the San Gabriel Valley
Water Company for relocation of an existing domestic water line;
and,
A. Authorize the Director of Finance to appropriate $45,000.00 from
Fund No. 275 and to make the necessary budget adjustments; and,
5. Authorize the Director of Public Works to execute contract change
orders for the additional work and suspended project incurred fees
with Stance Construction Company using approved project
contingency and appropriations.
STAFF REPORT