BUDGET INCREASE AND CHANGE ORDER NO. 124 – PULICE CONSTRUCTION,
INC. – SOTO STREET BRIDGE OVER VALLEY BOULEVARD AND UNION PACIFIC
RAILROAD PROJECT
Recommending the Board:
1. AUTHORIZE $1,200,000 in additional contingency and approve a revised
construction budget of $18,366,660.42 for the Soto Street Bridge over Valley
Boulevard and Union Pacific Railroad Project ;
2. AUTHORIZE the City Engineer to issue Change Order No. 124 for a notto
exceed amount of $1,246,182 for time related costs incurred by Pulice
Construction, Inc. due to delays during the construction of the Project; and
3. AUTHORIZE the City Engineer to issue subsequent change orders up to the
revised construction budget of $18,366,660.42 for the Project.
(W.O. E700070F, C131879)