Agenda Item
· Santa Monica
City Council — Item L
Original agenda text
Order of Business 5
L. Award Construction Bid to Access Pacific, Inc. for Wilshire Boulevard Safety Improvements Project
Phase 2A New Item Received. 1/19/2024
Recommended Action
Staff recommends that the City Council:
1. Adopt a finding of Categorical Exemptions pursuant to Sections 15301 and 15311 of the
California Environmental Quality Act (CEQA) Guidelines and Section 21080.25 of CEQA.
2. Award Bid #SP2669 to Access Pacific, Inc. for the construction of the Wilshire Boulevard
Safety Improvements Phase 2A Project for the Public Works Department.
3. Authorize the City Manager to negotiate and execute an agreement with Access Pacific,
Inc. for an amount not to exceed $1,711,848 (including a 10% contingency).
4. Authorize the Director of Public Works to issue any necessary change orders to complete
additional work within contract authority.
5. Authorize budget changes as outlined in the Financial Impacts and Budget Actions
section of this report.
a. Pedestrian Action Plan
b. Wilshire Safety Study Adoption
c. Oaks Initiative Form - Access Pacific