21. CONTRACT AMENDMENT: PROFESSIONAL SERVICES FOR THE ASSESSMENT
AND PLANS SPECIFICATIONS AND COST ESTIMATES FOR THE CITYWIDE BUS
STOP IMPROVEMENTS PROJECT – F2M21-68, C2M22-7, M2M24-77
10
5-13-24
On March 14, 2022, the City Council awarded a contract to Huitt-Zollars, Inc. to provide
assessment and professional design services for the Citywide Bus Stop Improvements
Project in the amount of $117,965.00. Due to an increased scope of work during the
preparation of the Plans, Specifications and Estimates, it was determined that additional
preparation, research and design for the project was necessary to complete the scope.
This additional work is an unforeseen change to the original contract; as such, staff is
recommending an increase of $20,000.00. All other provisions of the contract remain
unchanged.
Recommended Action: City Council approve an amendment, subject to final
language approval by the City Manager and City Attorney, to the contract with Huitt-Zollars
Inc. (C2M22-7) for the Assessment and Professional Design Services for the Citywide Bus
Stop Improvements Project; appropriate funding of $20,000.00 from the Prop A fund
balance, for a total contract amount of $137,965.00; and, direct staff to undertake the steps