16. NOTICE OF COMPLETION: 2024 EMERGENCY ROOF REPAIR PROJECT – F2M24-
36, C2M24-14, M2M24-117
On March 11, 2024, the City Council ratified the award of contract to Wiltshire Urethane
Foam Company for the 2024 Emergency Roof Repair Project in the amount of
$367,992.00. There was one negative change order issued in the amount of $3,000.00,
resulting in a final cost of $364,992.00. This project has been inspected by staff and all
work has been completed in accordance with the City’s requirements and specifications.
As such, it would be appropriate for the City Council to accept this project as complete
and instruct that the Notice of Completion be filed with the County of Los Angeles
Recorder’s Office.
Recommended Action: City Council accept the work of Wiltshire Urethane Foam
Company for the 2024 Emergency Roof Repair Project as complete in the amount of
$364,992.00; direct the City Clerk to file a Notice of Completion with the County of Los
Angeles for recordation; instruct the Finance Director to release the 5% retention 35 days
from the date of recordation if no liens are filed; and, direct staff to undertake the steps
necessary to finalize Council’s action. (M2M24-117)
10
7-22-24