Agenda Item · Alhambra

City Council — Item 20

Alhambra August 26, 2024 City Council Item 20
Original agenda text Item
20. NOTICE OF COMPLETION: 6th STREET SEWER MAIN REPLACEMENT PROJECT- PHASE II – F2M21-47, C2M23-79, M2M24-148 On October 9, 2023, the City Council awarded a contract to Ramona Inc. for the Sixth Street Sewer Main Replacement Project - Phase 2 in the amount of $1,168,950.00. There were two authorized change orders during the project. The change orders were to repair the damaged sewer main at 803 South Olive Avenue, asphalt trench repair due to water main leak on 4th Street, and also included various miscellaneous items credited to City. The change order increased the total amount of the contract by $39,209.61, for a total project cost of $1,208,159.61. The project has been completed in accordance with the City’s requirements and specifications. As such, it would be appropriate for the City Council to accept the project as complete and instruct the City Clerk that the Notice of Completion be filed with the County of Los Angeles Recorder’s Office. Recommended Action: City Council accept the work of Ramona Inc. for the Sixth Street Sewer Main Replacement Project - Phase 2 as complete in the amount of $1,208,159.61; direct the City Clerk to file a Notice of Completion with the County of Los Angeles for recordation; instruct the Finance Director to release the five percent retention 35 days from the date of recordation if no liens are filed; and direct staff to undertake the steps necessary to finalize Council’s action. (M2M24-148)