23. NOTICE OF COMPLETION: MAIN STREET, FOURTH STREET, AND MISSION ROAD
SEWER MAIN REPLACEMENT PROJECT - PHASE 1 – F2M22-53, C2M23-48, M2M24-
126
On June 26, 2023, the City Council awarded a contract to Toro Enterprises, inc., for the
Main Street, 4th Street, and Mission Road Sewer Main Replacement Project - Phase 1 in
13
7-22-24
an amount not to exceed $3,515,580.00. There were two authorized change orders during
the project. The change orders involved the installation of an additional 48-inch diameter
sewer drop manhole on Mission Rd., and also included various miscellaneous items
credited to City. The change order decreased the total amount of the contract by
$17,109.05, for a total project cost of $3,498,470.95. The project has been completed in
accordance with the City’s requirements and specifications. As such, it would be
appropriate for the City Council to accept the project as complete and instruct the City
Clerk that the Notice of Completion be filed with the County of Los Angeles Recorder’s
Office.
Recommended Action: City Council accept the work of Toro Enterprises Inc., for the
Main Street, 4 Street, and Mission Road Sewer Main Replacement Project – Phase 1
as complete in the amount of $3,498,470.95; direct the City Clerk to file a Notice of
Completion with the County of Los Angeles for recordation; instruct the Finance Director
to release the five percent retention 35 days from the date of recordation if no liens are
filed; and, direct staff to undertake the steps necessary to finalize Council’s action.
(M2M24-126)