Baldwin Park
City Council
9. Accept Construction Improvements and Authorize the Filing of a Notice of
Completion for City Project, CIP 22-040 Calino Avenue Sewer and Storm
Drain Improvements
It is recommended that the City Council:
1. Accept the construction improvements by Gentry General
Engineering Company of Colton, CA and Authorize recordation of a
Notice of Completion for City Project CIP 22 â040 Calino Avenue
Sewer and Storm Drain Improvements; and,
2. Authorize the release of retention funds in the amount of up to
$44,197.66 to Gentry General Engineering Company upon the
expiration of 35-day notice period; and,
3. Authorize expenditure in the amount of $21,000 from the available
balance of the approved project budget in Account No. 275-50-752-
58100-55021 to cover cost overruns related to the construction
change orders and close-out of the project.
4. Authorize the Director of Finance to make the appropriation and
necessary budget adjustments.
PUBLIC HEARING
REPORTS OF OFFICERS