REVISED TASK ORDER SOLICITATION (TOS) NO. 104 AND NO. 106, UNDER
CONTRACT AMENDMENT NO. 5 â FSY ARCHITECTS, INC.
Recommending the Board:
1. AUTHORIZE the City Engineer to issue a revision of the task for TOS No.
104 to FSY Architects, Inc. (FSY), increasing the budget authority from
$821,260 to $833,432 for architectural/engineering services for the Vision
Theatre  Manchester Junior Center Arts Project;
2. AUTHORIZE the City Engineer to issue a revision of the task for TOS No.
106 to FSY, increasing the budget authority from $946,000 to $1,133,828 to
provide architectural/engineering design and construction administration
services for the Project Phase Nos. 2, 3, 4 and 5; and
3. APPROVE the revised status of funding tables contained in this report.
104 to FSY Architects, Inc. (FSY), increasing the budget authority from
$821,260 to $833,432 for architectural/engineering services for the Vision
Theatre  Manchester Junior Center Arts Project;
2. AUTHORIZE the City Engineer to issue a revision of the task for TOS No.
106 to FSY, increasing the budget authority from $946,000 to $1,133,828 to
provide architectural/engineering design and construction administration
services for the Project Phase Nos. 2, 3, 4 and 5; and
3. APPROVE the revised status of funding tables contained in this report.
Table IV: PreviouslyÂApproved Funding Appropriation for TOS Nos. 104 and 106
Budget
Fiscal Fund No./ Fund Appropriation Unit Approved Increase/
Year Dept. No. Name No. Amount Decrease Total
PY36 424/22 CDBG 22G418 $711,260 $0 $ 711,260
PY38 424/22 CDBG 22J418 $110,000 $0 $ 110,000
TOS No. 104 Total $ 821,260
2007 424/22 CDBG 22A709 $296,000 $0 $ 296,000
2015 298/50 MICLA 50PTVT $250,000 $0 $ 250,000
2019 298/50 MICLA 50RTVT $200,000 $0 $ 200,000
2019 298/50 MICLA 50RTSF $200,000 $0 $ 200,000
TOS No. 106 Total $ 946,000
TOS Nos. 104 and 106 TOTAL $1,767,260
Table V: Revised Funding Appropriation for TOS Nos. 104 and 106
Budget Fiscal
Year Fund No. Fund Appropriation Unit Approved Increase/
Name No. Amount Decrease Total
PY36 424/22 CDBG 22G418 $711,260 $0 $ 711,260
PY38 424/22 CDBG 22J418 $110,000 $0 $ 110,000
2007 424/22 CDBG 22A7091 $ 12,172 $0 $ 12,172
TOS No. 104 Total $ 833,432
2007 424/22 CDBG 22A7091 $283,828 $0 $ 283,828
2018 298/50 MICLA 50PTVT $250,000 $0 $ 250,000
2019 298/50 MICLA 50RTVT $200,000 $(20,000) $ 180,000
2023 298/50 MICLA 50WPAA $200,000 $0 $ 200,000
2019 682/50 BOE 50RVDJ2 $0 $220,000 $ 220,000
(PHASE 5)
TOS No. 106 Total $1,133,828
TOS Nos. 104 and 106 Total $1,967,260
1. Funding source associated with TOS Nos. 104 and 106.
2. Funding source associated with Phase No. 5 added scope and additional contingency.
(W.O. E170378D, CÂ106420)
ADMINISTRATIVE ITEM(S)
2019 682/50 BOE 50RVDJ2 $0 $220,000 $ 220,000
(PHASE 5)
TOS No. 106 Total $1,133,828
TOS Nos. 104 and 106 Total $1,967,260
1. Funding source associated with TOS Nos. 104 and 106.
2. Funding source associated with Phase No. 5 added scope and additional contingency.
(W.O. E170378D, CÂ106420)