Huntington Beach
City Council
17. 24-336 Accept the lowest responsive and responsible bid and authorize
execution of a construction contract with US Builders and
Consultants Inc. in the amount of $579,600 for the Storm Water Pump
Station Roof and Facilities Improvements Project, CC-1739 and
appropriation of funds
Recommended Action:
A) Accept the lowest responsive and responsible bid submitted by US Builders and
Consultants Inc. in the amount of $579,600; and ,
B) Authorize the Mayor and City Clerk to execute a construction contract in a form
approved by the City Attorney; and ,
C) Appropriate $356,864 from Planned Local Drainage Fund undesignated fund balance
to Drainage Fund account 21188009.82500.