17. AWARD OF CONTRACT FOR SLOPE REPAIR AT SUNSET AVENUE,
SOUTH OF 10TH AVENUE
Recommendations:
(1) Award and authorize the City Manager to execute a contract with Horizons
Construction in the amount of $1,019,055 for construction of the Sunset Avenue
Slope Repairs;
(2) Authorize the City Manager to approve project-related expenses, and
construction change orders for unforeseen circumstances for an amount not to
exceed $100,000; and
(3) Approve the transfer of an appropriation of $252,000 from the Summit Drive
Storm Drain Construction Project to the Sunset Avenue Slope Repair Project,
bringing the total project budget to $1,202,000.