6F. AWARD OF CONSTRUCTION CONTRACT FOR THE FISCAL YEAR (FY) 2023/24
CITYWIDE STREET RESURFACING PROJECT (TASK CODE NO. 2024-101) AND
APPROPRIATION OF FUNDS
Eight bids for the FY 2023/24 Citywide Street Resurfacing Project were opened on
February 4, 2025. Based on the post-bid analysis of the bids received, staff has
determined the bid submitted by R.J. Noble Company to be the lowest responsible and
responsive bid at $1,224,741.77. An appropriation of $585,000 from the City’s Gas Tax
Fund’s (#211) fund balance is needed to fund this contract.
RECOMMENDED ACTION:
1. City Council find that this project is exempt from the California Environmental Quality
Act (“CEQA”), Class 1, and 15301(c) as repair, maintenance, and minor alteration of
existing streets, sidewalks, gutters, and similar facilities; and
2. Accept Dash Construction Company, Inc.’s Request for Withdrawal of Bid; and
3. Award a construction contract for the FY 2023/24 Citywide Street Resurfacing Project
to R.J. Noble Company for the bid amount of $1,224,741.77 and reject all other bids;
and
4. Authorize the City Manager to bind the City of Stanton and R.J. Noble Company in a
contract for the construction; and
March 11, 2025
5. Authorize the City Manager to approve contract change orders, not to exceed
$122,474; and
6. Appropriate $585,000 from the City’s Gax Tax Fund (#211) to increase the Fiscal Year
2024-25 budget for this project from $824,083 to $1,409,083.