Agenda Item
· Santa Clarita
City Council — Item 8
Original agenda text
Item
8. DOCKWEILER DRIVE EXTENSION, PROJECT S3023 - DESIGN CONTRACT
MODIFICATIONS - This item considers extending the current contracts to provide
design services for the Dockweiler Drive Extension project. The project includes design
of Dockweiler Drive from the existing terminus to 13th Street and Railroad Avenue.
RECOMMENDED ACTION:
City Council:
1. Extend the current design contract and authorize an increased expenditure authority
for design services with MNS Engineers, Inc., in the amount of $1,668,812 and
Page 5
authorize a contingency in the amount of $166,881, for a revised total contract
amount not to exceed $4,882,236.
2. Extend the current design services agreement and authorize an increased expenditure
authority for design services with Southern California Regional Rail Authority, in the
amount of $301,400 and authorize a contingency in the amount of $30,140, for a
revised total contract amount not to exceed $572,935.
3. Appropriate one-time funds in the amount of $2,100,000 from the Via Princessa
Bridge and Thoroughfare Fund (Fund 453) to expenditure account S3023453-516101,
Dockweiler Drive Extension.
4. Authorize the City Manager or designee to execute all contracts and associated
documents, subject to City Attorney approval.