15. NOTICE OF COMPLETION: MEN'S RESTROOM REMODEL AT THE ALHAMBRA
CITY YARD PUBLIC WORKS BUILDING – F2M20-66, C2M24-40, M2M25-49
On June 24, 2024, the City Council awarded a contract to Sanz Construction for the City
Yard Public Works Building Restroom Project in the amount of $152,200.00. One change
order, amounting to $13,125.00, was issued for the project to install new walls and
additional plumbing. This project was inspected by staff and all work was completed in
accordance with the City’s requirements and specifications. As such, it would be
appropriate for the City Council to accept this project as complete and instruct the Notice
of Completion be filed with the County of Los Angeles Recorder’s Office.
Recommended Action: City Council accept the work of Sanz Construction for the
remodeling of the men's restroom at the Alhambra City Yard project as complete in the
amount of $165,325.00; direct the City Clerk to file a Notice of Completion with the County
of Los Angeles for recordation; instruct the Finance Director to release the 5% retention
35 days from the date of recordation if no liens are filed; and, direct staff to undertake the
steps necessary to finalize Council’s action. (M2M25-49)