San Clemente
City Council
I. CONTRACT AWARD - SOUTH EL CAMINO REAL LANE
RECONFIGURATION AND BUFFERED BIKE LANE PROJECT FROM
AVENIDA MENDOCINO TO SOUTH CITY LIMIT, APPROVING A
SUPPLEMENTAL APPROPRIATION IN THE AMOUNT OF $848,900 AND
MAKING FINDINGS UNDER THE CALIFORNIA ENVIRONMENTAL QUALITY
ACT
Staff Recommendation
Adopt Resolution No. 25-53, which will:
1. Make findings under the California Environmental Quality Act that no further
environmental review is required.
2. Approve a supplemental appropriation of $848,900 from the Gas Tax Fund
into Account No. 012-861-45300-000-11308.
3. Reject Diamond Construction & Design, Inc.'s bid as non-responsive and
Award the South El Camino Real Lane Reconfiguration & Buffered Bike
Lane Project, Federal Project No. CML-5274(039), FTIP No. ORA
190914, City CIP Project No. 11308, contract to ONYX Paving Company,
Inc. as the lowest responsive and responsible bidder.
4. Approve, and authorize the City Manager to execute, Contract No. C25- 19,
by and between the City of San Clemente and ONYX Paving Company, Inc.,
providing for for the South El Camino Real Lane Reconfiguration & Buffered
Bike Lane Project, in an amount not to exceed
$1,639,000, in a form substantially similar to Contract No. C25-
19(Attachment 6).
5. Approve a 10% construction contingency of $163,900 for this project.