City Council — Item L
Original agenda text
Order of Business 9
9L.
ACCEPTANCE OF THE 8880 PACIFIC AVENUE DEMOLITION AND ABATEMENT
PROJECT BY THE CITY COUNCIL OF THE CITY OF STANTON, CALIFORNIA
The demolition and abatement of the vacant four-unit building located at 8880 Pacific
Avenue has been successfully completed. The final construction cost for this portion of
the overall project was $75,000. The City Engineer has certified that all work was
completed in accordance with project specifications as of June 3, 2025. Staff
recommends the City Council formally accept the completed improvements, approve the
final contract amount, and authorize the filing of the Notice of Completion.
RECOMMENDED ACTION:
1. City Council find that the project is categorically exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301(l)(3), Class 1 – minor
alteration and demolition of existing small structures; and
2. Accept the completed improvements for the 8880 Pacific Avenue Demolition and
Abatement Project as certified by the City Engineer, and establish June 3, 2025, as
the official date of completion; and
3. Approve the final construction contract amount of $75,000 with Integrated Demolition
and Remediation, Inc.; and
4. Direct the City Clerk to file the Notice of Completion with the Orange County ClerkRecorder within ten (10) days of project acceptance (Attachment A); and
Stanton City Council Agenda
5. Authorize City staff to release the retention payment of $3,750 to Integrated
Demolition and Remediation, Inc. following the statutory 35-day lien period after filing
of the Notice of Completion.