APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE
ADVERTISEMENT FOR BIDS FOR THE MAIN STREET AND OLD
TOWN IMPROVEMENTS PROJECTS The plans and specifications for
the Main Street Improvements Project and the Old Town Improvements
Project have been completed, and the projects are now ready for bid.
Construction is anticipated to begin in November 2025, with completion
estimated in Summer 2026.
Recommendation: It is recommended that the City Council adopt
Resolution No. 25-15 approving the plans and specifications for the Main
Street Improvements Project and the Old Town Improvements Project and
authorize the City Clerk to advertise to receive bids. Fiscal Impact: The
City Council approved the Fiscal Year 2025-2026 Capital Improvement
Program on June 3, 2025, which includes funding in the amount of
$7,000,000 for the Main Street Improvements Project and $3,993,741 for
the Old Town Improvements Project. The engineer’s estimates are
$6,820,000 for the Main Street Improvements Project and $4,370,000 for
the Old Town Improvements Project. As the bids are received and verified,
staff will bring back a recommendation to award a contract, and if
necessary appropriate additional funding from Measure M2 and Gas Tax
funds to complete the projects.