Agenda Item
· Newport Beach
City Council — Item 11
Original agenda text
Item
11.
a) Find this project exempt from the California Environmental Quality Act (CEQA)
pursuant to Section 15302(c), Class 2 (reconstruction of existing facility involving
negligible or no expansion of capacity) of the CEQA Guidelines, because this
project has no potential to have a significant effect on the environment;
b) Approve the project plans and specifications;
c) Award Contract No. 9835-1 to T.E. Roberts, Inc. for the total bid price of
$6,741,473 for the Balboa Peninsula Water Main Replacement, East Irvine
Terrace Water Main Replacement & Shorecliff Community Water System
Improvements - Phase 2 project, and authorize the Mayor and City Clerk to
execute the contract; and
d) Establish a contingency of $1,350,000 (approximately 20% of total bid) to
cover the cost of unforeseen work not included in the original contract.
Staff Report
Attachment A - Location Maps
Balboa Island Water Main Replacement – Phase 3 & Shorecliff Community
Water System Improvements - Notice of Completion for Contract No. 7173-3