NOTICE OF COMPLETION: ROOF REPLACEMENT AT ALHAMBRA FIRE STATION
74 PROJECT – F2M24-36, C2M25-21, M2M25-163
On February 10, 2025, the City Council authorized the issuance of a Notice Inviting Bids
for the roof replacement project at Alhambra Fire Station 74, located at 2505 W. Norwood
Place. The contract was awarded to Superior Roofing Systems, Inc. in the amount of
$125,256.00 on May 12, 2025. There were three change orders to the project. Change
order No. 1 was in the amount of $45,360.00 for a change in roof material, from a onelayer flat tile to a two-piece clay tile. Change order No. 1 is the net amount after the credit
of $18,495.00 for the return of the original flat tile material. Change order Nos. 2 and 3
were for the plywood replacement in the upper deck and perimeter edge in the amount of
$51,360.00. All change orders were approved by City Council on August 25, 2025. All
work has been completed in accordance with the project specifications. It would be
appropriate for City Council to accept this project as complete and instruct that the Notice
of Completion be filed with the County of Los Angeles Recorder’s Office.
Recommended Action:
City Council accept the work of Superior Roofing Systems,
Inc. for the roof replacement project at Alhambra Fire Station 74 as complete in the amount
of $221,976.00; direct the City Clerk to file the Notice of Completion with the County of
Los Angeles for recordation; instruct the Finance Department to release the five percent
(5%) retention thirty-five (35) days from the date of recordation, if no liens are filed; and,
direct staff to undertake the steps necessary to finalize the Council’s action. (M2M25-163)