NOTICE OF COMPLETION: ROOF REPLACEMENT AT THE UTILITIES CUSTOMER
SERVICE CENTER – F2M24-69, C2M25-7, M2M25-137
The City Council awarded a contract to McDonnell Roofing, Inc. in the amount of
$64,400.00 for the roof replacement at the Customer Service Center on February 24,
2025. There was one change order in the amount of $6,800 to remove two drains that
were leaking and replace two 3-inch cast iron drains. In addition, $892.00 is being
deducted to the retention as a result of damage to the cable and connection to the front
building’s camera. All work has been completed in accordance with the project
specifications. It would be appropriate for City Council to accept this project as complete
and instruct that the Notice of Completion be filed with the County of Los Angeles
Recorder’s Office.
Recommended Action:
City Council accept the work of McDonnell Roofing, Inc. for
the Roof Replacement Project at the Customer Service Center as complete in the amount
of $70,308.00; direct the City Clerk to file the Notice of Completion with the County of Los
Angeles for recordation; instruct the Finance Director to release the 5% retention thirtyfive (35) days from the date of recordation, if no liens are filed; and, direct staff to undertake
the steps necessary to finalize the Council’s action. (M2M25-137)