Original agenda text Order of Business B
B.10. INCREASE IN PROJECT CONTINGENCY FOR THE CITY’S CONTRACT WITH BALI CONSTRUCTION FOR THE RULE 20B OVERHEAD TO UNDERGROUND CONVERSION LA PEER DRIVE & ALMONT DRIVE, CIP 2204 [H. COLLINS, J. GILMOUR]: SUBJECT: The City Council will consider increasing the project contingency for the Rule 20B Overhead to Underground Conversion La Peer Drive & Almont Drive, CIP 2204, by 5% ($178,611.80) to account for changes in the construction Agreement due to unforeseen conditions, for a total not to exceed contingency amount of 25% ($ 893,059.00). RECOMMENDATION: Authorize a $178,611.80 increase in the contingency amount for Construction Services with Bali Construction, for a new not to exceed contingency amount of $893,059.00 and authorize the City Engineer to approve change orders to the agreement for services.